Skip to main content
European Commission logo
European Climate, Infrastructure and Environment Executive Agency

Reports & payment requests

Reports & payment requests (REPA): The periodic report is to be submitted 60 days after the end of each reporting period. In justified cases, CEF beneficiaries may request an extension of this period.
The request shall be submitted in SyGMa (My Projects > Actions > Manage Project > Process Communications) and the extension that can be granted will not exceed 120 days of additional time (on top of the 60 days) to submit the periodic report. As beneficiary, you are invited to preferably inform CINEA Project Officer (PO) of your intention to request such an extension introducing the request in SyGMa.

In line with article 24.2(a) of the Grant Agreement, all Entities (Beneficiary or Affiliated Entity) must submit a Certificate on the financial statements (CFS) when the threshold is reached in accordance with article 4.3 of the data sheet. The template is available in the Funding&Tender (F&T) portal and guidance in the Annotated Grant Agreement (Art.24.2 and annotations). 

In addition, please note:

 -> The CFS threshold requirement is cumulative. Hence, to calculate if the threshold is reached, previous REPAs where CFS was not submitted should also be taken into account. This means that for a REPA submitted in the year N it will be checked if:

  •  The CEF contribution requested by the REPA submitted in the year N, 

PLUS 

  • The CEF contribution requested by ANY previous REPA prior to the year N where a CFS was not requested, is cumulatively at least 325,000€.

  ->  In case a CFS shall be submitted along with a REPA  for instance the year N, the CFS shall cover: 

  • the costs declared in the REPA submitted in the year N 

AND

  • the costs declared in ANY previous REPA prior to the year N where a CFS was not requested.

 ->  At the top of the first page the CFS template provides the instruction that the CFS is “to be filled out by the CFS auditor, printed on their own letterhead and signed (on paper). The scanned PDF should be submitted by the beneficiary through the Portal (both for themselves and their affiliated entities).”. “Signed (on paper)” means that the auditor can provide the CFS either as an e-signed PDF or signed in blue-ink (and scanned).

 ->  When submitting (uploading) the signed CFS it is important to include all pages of the template including the Terms of reference and the Certificate itself.

It is to be noted that eGrant allows to upload one file only. Therefore, in case of e-signed PDF files, the electronic signature may no longer comply with the e-signature validation requirements. If so, Beneficiaries are advised to also send CFS files through the Communication portal. 

 ->  A qualified independent public officer is allowed to perform the CFS under the Connecting Europe Facility of private law entities if a public (State, region or municipality) body has control over this entity, which is owned 50% or more by that public body.

Guidance on the eligibility of costs is available in the Annotated Grant Agreement.

For the eligibility of costs related to subcontracting work/services outside the eligible or target countries that are mentioned in the call text, please read the respective FAQ.

The reporting process for CEF Actions can be found at Reporting Process – Connecting Europe Facility (CEF) Action Grants.
The periodic report is to be submitted directly in the Periodic Reporting Module of the Portal (My Projects > Actions > Manage Project > Periodic Reporting > )

This module will become accessible at the end of each Reporting Period.

Composition of periodic report

Technical Report.

Find the template for the Technical Report at CEF Reference Documents (Templates&forms > Project report templates > Periodic Report (CEF)).

Please note that:

-> Part A of the Technical Report will be automatically filled in with data extracted from SyGMa and also includes data from the Continuous Reporting;

-> Part B of the Technical Reporting is composed of:

  • A descriptive part, whose template can be downloaded as a Word file directly from the Tab Tech. Report (Part B) of the Project Periodic Report.
  • A Budget Forecast per WP, whose template can be downloaded as an Excel file directly from the Tab Tech. Report (Part B) of the Project Periodic Report.

 Financial Report

A Financial Report is needed individually for each Beneficiary and Affiliated Entity declaring costs.

The templates for the financial part of the Financial Report and the CFS, where applicable, are available at CEF Reference Documents (Templates&forms > Project report templates > detailed cost reporting table / Certificate on the Financial Statement (CFS)). The detailed cost reporting table can also be downloaded as an Excel file directly from the Periodic Reporting Module of the Portal.

After validation of the Financial Report, each Beneficiary and Affiliated Entity declaring costs will have to upload a Budget Forecast per RP. This template is available at CEF Reference Documents  (Templates&forms > Project report templates > …) and can also be downloaded as an Excel file directly from the Periodic Reporting Module of the Portal.

The reporting process for CEF Actions can be found at Reporting Process – Connecting Europe Facility (CEF) Action Grants.

First, please make sure that the information in the Continuous Reporting Module is updated. Then, please follow the steps listed in the Reporting Process.

Regarding Part B of the technical report, please download, fill-in and upload the template available this task is to be carried out under the Tab Tech. Report (Part B) of the Project Periodic Report.

Please ensure coherence of the information (e.g. number of reporting periods and associated costs) provided in the Budget Forecast per RP (under Financial Report), in the Budget Forecast per WP (under Part B of the Technical Report) and the Technical Progress (under the Continuous Reporting).

N.B: For Grant Agreements where the grant takes the form of Unit Contributions (ERTMS, AFIF EVRI and RFN) or lump sum, please note that Beneficiaries and Affiliated Entities do not need to include in the Periodic Report:

  1. the Budget Forecast per WP (under Part B of the Technical Report),
  2. the Budget Forecast per RP (under Financial Report),
  3. the Certificate on the Financial Statement (CFS).

Moreover, dedicated templates for the financial part of the Financial Report are available at CEF Reference Documents (Templates & forms > Project report templates > Cost Reporting Calculator …).